How to use this tool
- Measure the path run — overall length, and the finish width (3–4 ft feels comfortable for two people; 2 ft is a tight garden stroll).
- Split curves into straight sections and calculate each; the waste factor absorbs the gentle bends between them.
- Keep 4 in thickness (3 in only on very well-prepared base for pure foot traffic).
- Compare bags with ready-mix. Walkways are the classic bag project: a 3 × 30 ft path at 4 in is under 1.2 yd³.
How the result is calculated
Volume (ft³) = length (ft) × width (ft) × thickness (ft) × number of areas, multiplied by your waste factor, then divided by 27 for cubic yards. Circular areas use π × (diameter ÷ 2)². Bag counts use standard US yields: an 80 lb bag yields about 0.60 ft³ of mixed concrete, a 60 lb bag about 0.45 ft³.
Choosing the right numbers
Common walkway sizes at 4 in thick with 10% waste:
| Path | Size | Concrete | 80 lb bags |
|---|---|---|---|
| Garden stroll | 2 ft × 20 ft | ≈ 0.55 yd³ | ≈ 25 |
| Front path | 3 ft × 30 ft | ≈ 1.11 yd³ | ≈ 51 |
| Wide entry walk | 4 ft × 40 ft | ≈ 1.97 yd³ | ≈ 91 |
Details worth the effort: tool a control joint every 3–4 ft of width in length (roughly every 3 ft for a 3 ft path is overkill — the rule of thumb is joints at 2–3× the width in feet), slope the walk ¼ in per foot to shed water toward the yard, and finish with a light broom texture for wet-weather grip.
Common mistakes to avoid
- Too thin. 2 in paths crack into plates within a couple of winters. Four inches with a compacted base is the floor.
- No joints. Long narrow slabs crack lengthwise without joints. Tool them in while the surface is still thumb-printable.
- Steep driveway crossings without thickening. Where the walk crosses a driveway apron, thicken to 5–6 in or the car will break it.
- Wide bags-only pours in hot weather. Concrete sets fast above 80 °F; a 90-bag pour needs a crew, not a solo effort.
Worked examples
Example — 3 ft × 30 ft front path, 4 in
Area = 90 ft². Volume = 90 × ⅓ = 30 ft³. With 10% waste = 33 ft³ ≈ 1.22 yd³ — about 55 of the 80 lb bags, or one short ready-mix load.
Frequently asked questions
How many bags of concrete for a 3×30 walkway?
About 55 of the 80 lb bags at 4 in thick with 10% waste — or roughly 1.25 cubic yards of ready-mix if a short-load delivery makes sense for you.
How wide should a walkway be?
3–4 ft lets two people walk abreast and is the usual front-path width. 2 ft works for informal garden paths.
How often do I need control joints?
Aim for joint spacing of about 2–3 times the slab width in feet — every 6–9 ft on a 3 ft walk — and never let a joint run area exceed roughly 100 ft².
Assumptions, sources and limits
- Uniform thickness on a compacted base; no allowance for steps, landings or driveway crossings (calculate those separately and add).
- Bag yields: standard US figures (80 lb ≈ 0.60 ft³, 60 lb ≈ 0.45 ft³).
- General practice only — municipal sidewalks may have specified thickness and mix requirements.
Planning estimates only.