Post Hole Concrete Calculator

Quote a single post hole or an entire fence line: the tool deducts the post itself, the gravel base and the dry gap at the top, then converts to the bag size you actually buy.

Hole diameterDepth
Quick presets:
Please check this value.
Please check this value.
Please check this value.
A 4×4 post is 3.5 in square; a 6×6 is 5.5 in. Round steel posts: use their diameter. Leave blank for a bare anchor. Please check this value.
Drainage layer under the post — 6 in is standard and not filled with concrete. Please check this value.
Depth left unfilled so soil or a mounded collar can sit over the concrete. Please check this value.
Optional — fills the hole count from length and spacing below. Please check this value.
Typical fence spacing is 6–8 ft on center. Please check this value.
Small holes hide less error — 5% is plenty. Please check this value.
Please check this value.
Please check this value.

How to use this tool

  1. Measure one hole. Diameter and depth as drilled. A one-man auger makes 8–12 in holes; a two-man auger or rental reaches 12–18 in, which is where gate and corner posts belong.
  2. Add the post width so the tool can deduct the wood or steel from the volume — it makes a real difference across a 40-post fence line.
  3. Keep 6 in of gravel in the defaults. That layer is drainage, not concrete, and stays in the hole untouched.
  4. For a fence run, enter the total length and your spacing; the tool replaces the hole count, adding one for the end post.
  5. Pick the bag size you will actually carry. Fast-setting 50 lb bags cost a premium per foot but skip the mixing tub entirely.

How the result is calculated

Per hole: concrete volume = π × (hole diameter ÷ 2)² × filling depth − post cross-section × filling depth, where the filling depth is the hole depth minus the gravel base and the gap left at the top. Square posts are deducted at their actual width (a "4×4" is 3.5 in); round posts likewise if you enter the diameter.

The line total multiplies by the number of holes — either typed directly, or derived from fence length ÷ post spacing, rounded up, plus one for the far end post — then applies your waste factor. Bag counts use standard US yields: 80 lb ≈ 0.60 ft³, 60 lb ≈ 0.45 ft³, 50 lb ≈ 0.375 ft³, 40 lb ≈ 0.30 ft³.

Choosing the right numbers

Two rules decide a post hole: one-third below grade (a 6 ft fence wants ~2 ft of post in the ground) and roughly 3× the post width in hole diameter for bellied strength. Typical combos:

PostHole diameterHole depth80 lb bags each*
4×4, 6 ft fence panel10–12 in36 in≈ 2
4×4 corner / gate12–18 in42 in≈ 3–4
6×6 deck or gate post16–18 in42–48 in≈ 4–5
Steel line post (2⅜ in)8–10 in30–36 in≈ 1

*With a 6 in gravel base and the post volume deducted, ~5% waste.

Set posts on the gravel, brace them plumb before the pour, and crown the concrete above grade slightly so water runs off instead of pooling against the post.

Common mistakes to avoid

  • Counting nominal lumber. A "6×6" is 5.5 in; deducting 6 in across 20 posts overstates the concrete only slightly, but a 4×4 (3.5 in actual) versus a 4×4 hole diameter leaves nothing to pour.
  • Skipping the gravel base. Concrete wicking water into the post end is how posts rot off in ten years.
  • Backfilling the last inch with concrete and burying it. Leave the gap or mound it above grade deliberately.
  • Assuming the first hole's count. Holes drilled with a hand auger wander; measure a few and use the average.
  • Buying exactly the bag count. Fast-set mixes set in 10–20 minutes — one ruined batch per post is common on hot days. Keep spare bags.

Worked examples

Example — single 4×4 gate post, 12 in × 42 in hole

Filling depth = 42 − 6 gravel = 36 in (3 ft). Hole = π × (0.5)² × 3 ≈ 2.36 ft³; post 3.5 in square deducts 0.25 × 3 ≈ 0.26 ft³. Net ≈ 2.1 ft³ → 4 bags of 80 lb with 5% waste.

Example — 100 ft fence, posts every 8 ft, 4×4 line posts

100 ÷ 8 = 12.5 → 13 spaces → 14 posts. Each hole (12 × 36 in, post deducted) ≈ 2.1 ft³. Total ≈ 29.4 ft³ with waste → 50 bags of 80 lb, about 1.1 yd³ loose.

Frequently asked questions

How many bags of concrete per fence post?

A 4×4 line post in a 12 in × 36 in hole with a 6 in gravel base takes about 2 bags of 80 lb mix; corner and gate posts in bigger holes take 3–5. The calculator above prices the whole run at once.

Should the post touch the bottom of the hole?

No. Set it on 6 in of gravel so water drains away from the end grain. The gravel base also gives you a clean reference surface for setting height.

Fast-setting or regular mix for posts?

Fast-set saves mixing and bracing time — pour dry, add water, done in minutes. Regular mix is stronger per bag and cheaper per foot, and lets you take longer plumbing the post. For gate posts (which swing and shake), many builders prefer regular mix and full bracing.

How deep should a fence post hole be?

Rule of thumb: one-third of the above-ground post height, and in freezing climates the bottom must be at or below the frost line or frost heave will lift the posts in a few winters.

Assumptions, sources and limits

  • Cylindrical holes of uniform diameter; augered holes in stony soil often flare — the waste factor covers modest flare only.
  • Square posts deducted at the width you enter; round posts treated as square of the same width (negligibly conservative).
  • Bag yields are the standard US figures (80 lb ≈ 0.60 ft³, 60 lb ≈ 0.45 ft³, 50 lb ≈ 0.375 ft³, 40 lb ≈ 0.30 ft³); fast-set brands vary slightly.
  • Frost depth still governs: in freezing climates the concrete must reach below the frost line regardless of what the fence panel needs.
  • Prices come only from your own input.

Planning estimates for non-structural posts. Deck footings and anything carrying structure belong on the footing calculator and your local code.