How to use this tool
- Measure the drive. Length is from street to garage or parking pad; width is across the driving surface. If the driveway widens at the top, run the tool twice — once for the approach, once for the pad — or use the larger width and keep the waste factor honest.
- Set thickness. The tool starts at 6 in, the sensible default for vehicles. 5 in works for light occasional parking; 6–7 in suits heavier SUVs and small trucks.
- Keep the waste factor at 10% unless the subgrade is fresh fill that may settle unevenly.
- Enter your local price to see the material line before delivery fees.
How the result is calculated
Volume (ft³) = length (ft) × width (ft) × thickness (ft) × number of areas, multiplied by your waste factor, then divided by 27 for cubic yards. Circular areas use π × (diameter ÷ 2)². Bag counts use standard US yields: an 80 lb bag yields about 0.60 ft³ of mixed concrete, a 60 lb bag about 0.45 ft³.
Choosing the right numbers
Common residential driveway footprints, at 6 in thick with a 10% waste factor:
| Layout | Size | Concrete (yd³) |
|---|---|---|
| Single-car lane | 10 ft × 20 ft | ≈ 3.7 |
| Single with parking pad | 10 ft × 30 ft | ≈ 5.6 |
| Double-car lane | 16 ft × 20 ft | ≈ 5.9 |
| Double with turning room | 20 ft × 20 ft | ≈ 7.4 |
Driveways live or die by what's underneath: a compacted gravel base of 4–6 in, good drainage away from the garage, and control joints cut or tooled at roughly 10 ft spacing. Where the drive meets the street, many municipalities require an apron detail — check before you pour.
Common mistakes to avoid
- Pouring at 4 in because the patio worked fine. Vehicles load edges differently; a car-rated slab is 5–6 in with a compacted base.
- Skipping the apron. The strip between sidewalk and street often has its own thickness and permit requirements.
- Measuring along the curve of a curved drive. Split a curved drive into two or three straight sections and calculate each one.
- Ordering exactly the calculated yards. Plants batch in quarter-yard steps; round up and confirm their short-load and return policies.
Worked examples
Example — 20 ft × 24 ft double driveway, 6 in
Area = 480 ft². Volume = 480 × 0.5 = 240 ft³. With 10% waste: 264 ft³ ≈ 9.78 yd³ — order 10 yards.
Example — 10 ft × 28 ft single lane, 5 in
Area = 280 ft². Volume = 280 × (5 ÷ 12) ≈ 116.7 ft³. With 10% waste ≈ 128.3 ft³ ≈ 4.75 yd³.
Frequently asked questions
How many yards of concrete for a 2-car driveway?
A 20 ft × 20 ft driveway at 6 in needs 400 ft² × 0.5 ft = 200 ft³, about 7.4 yd³ with a 10% waste factor — order 7.5 to 8 yards.
What thickness should a concrete driveway be?
5 in is the floor for passenger cars; 6 in is the comfortable default; use 6–7 in where SUVs, boats or light trucks will park. The compacted gravel base and edge support matter as much as thickness.
Bags or ready-mix for a driveway?
Ready-mix, in nearly every case. Even a small single-car drive is 3+ yards — over 150 bags of hand mixing that must all be finished in one pour.
Assumptions, sources and limits
- Geometry only: flat slab of uniform thickness on a prepared, compacted base. Slopes and crowns belong in the waste factor.
- Bag yields use standard US figures (80 lb ≈ 0.60 ft³, 60 lb ≈ 0.45 ft³). A driveway of almost any size will be a ready-mix job — bag counts are shown for comparison.
- Thickness defaults reflect common residential practice, not a code requirement or an engineering design for specific vehicles.
- Prices come only from your own input.
Estimates for planning only. Verify with your supplier; consult local codes for aprons, curbs and drainage.