How to use this tool
- Measure the total run. Walk the footing and add up every wall segment — for a rectangle, twice the length plus twice the width. Add internal crawlspace walls individually.
- Height runs from footing to wall top. Don't include the footing itself; it has its own calculator.
- Keep the 8 in default thickness unless the drawings say otherwise — 8 in is the residential norm, 10–12 in where the backfill is tall.
- Deduct the openings. Basement windows and doors are real volume; multiply each one's width by height and enter the sum in square feet.
- Enter the bolt spacing you plan — the code maximum is commonly 6 ft on center — and the tool orders the right count.
How the result is calculated
Volume (ft³) = total wall length (ft) × height (ft) × thickness (ft) − openings (ft²) × thickness (ft), times your waste factor, divided by 27 for cubic yards. Anchor bolts are estimated as total length ÷ spacing, plus one for the run's end — corner layouts in practice are set by the sill layout, so treat the count as an order quantity, not a placement plan.
Choosing the right numbers
Poured walls of a few common sizes, per 100 ft of run:
| Wall | Concrete per 100 ft |
|---|---|
| 8 in × 6 ft tall (crawlspace) | ≈ 3.7 yd³ |
| 8 in × 8 ft tall (single-story basement) | ≈ 4.9 yd³ |
| 10 in × 9 ft tall | ≈ 6.9 yd³ |
| 12 in × 10 ft tall (deep basement) | ≈ 11.1 yd³ |
What separates a wall pour from a slab pour is pressure: a 9 ft head of wet concrete pushes the forms outward with serious force, so form ties, bracing and pour rate are engineered, not improvised. Backfilling waits until the floor system (or a designed bracing plan) is in place — a freestanding cured wall can still crack from aloader pushing fill against it. Vertical reinforcement, wall thickness above 8 ft of height, and tall backfill are engineered items.
Common mistakes to avoid
- Forgetting openings. Four basement windows and a door in an 8 ft wall deduct real yards — on a 140 ft run the deduction is about a quarter yard each, and the plant will bill the difference.
- Measuring inside the foundation instead of centerline. Wall length runs along the middle of the wall; measuring room-inside dimensions understates the run by the wall thickness on every corner.
- Pouring and backfilling the same week. Fresh walls reach full strength in weeks; early backfill plus a loader's bump is the classic cracked-corner story.
- Skipping the bolt count. Anchoring the sill is a code item, and an extra bundle of bolts is cheaper than a second trip.
Worked examples
Example — 28 × 36 ft basement, 8 ft walls, 8 in thick, one 3×4 ft door + four 2×3 ft windows
Run = 2 × (28 + 36) = 128 ft. Gross = 128 × 8 × 0.667 ≈ 682.7 ft³. Openings = 12 + 24 = 36 ft² → deduct 24 ft³. Net ≈ 658.7 ft³; with 5% waste ≈ 691.6 ft³ ≈ 25.6 yd³.
Example — crawlspace ring, 8 in × 4 ft walls, 60 ft run
60 × 4 × 0.667 ≈ 160 ft³; with 5% waste ≈ 168 ft³ ≈ 6.2 yd³, and about 11 anchor bolts at 6 ft spacing.
Frequently asked questions
How many yards of concrete for a basement wall?
A common 28 × 36 ft basement — 128 ft of 8 in × 8 ft wall — needs roughly 25–26 yd³ after window and door deductions. Use the calculator with your actual run, height and openings.
Should I deduct window openings from the order?
Yes, at net framed size. The deduction on a typical basement is a yard or more. Crews usually pour the openings with buck frames in place, so the concrete genuinely stops there.
What thickness should a foundation wall be?
8 in is the residential standard for basement and crawlspace walls within common heights and backfills. Taller basements, heavy stories above, or tall backfill step up to 10–12 in — and at that point the design is engineered, not tabulated.
Bags or ready-mix for foundation walls?
Ready-mix, always. Even a small crawlspace ring is 5+ yards poured continuously around the forms; bags cannot keep pace and cold joints would ring the building.
Assumptions, sources and limits
- Straight prismatic walls of uniform thickness; pilasters, thickenings and bond-beam blocks are outside the estimate.
- Openings deducted at the net framed size you enter, running the full wall thickness.
- Anchor bolt count is a simple length ÷ spacing + 1 order estimate; actual layout follows the sill plan and local code.
- Bag yields use standard US figures (80 lb ≈ 0.60 ft³, 60 lb ≈ 0.45 ft³) — although any real foundation wall is a ready-mix job.
- Prices come only from your own input.
Planning estimates only. Wall height, thickness, reinforcement and backfill sequencing must follow your local code and the engineered drawings.