Concrete Pile Calculator

Volume for a pile run — straight bored shafts, or the under-reamed bell at the bottom that spreads the load — quoted per pile and for the whole group.

Inner diameterHeight
Please check this value.
From cut-off elevation to the shaft bottom — or to the bell top if belled. Please check this value.
Please check this value.
Bored holes in wet or caving soil swallow extra concrete — 10% is a fair start. Please check this value.
Leave blank for a straight shaft. Please check this value.
Vertical height of the belled section, typically 1–2 ft. Please check this value.
Please check this value.

How to use this tool

  1. Set the shaft diameter and length as drilled — length from cut-off elevation to the bottom of the straight section.
  2. Add the bell only if the design has one. An under-ream spreads the load at the bottom in weak soils; enter its diameter and vertical height and the shaft length should stop at the bell's top.
  3. Keep 10% waste unless the boring log is dry and clean — wet holes, sloughing sides and tremie pours all eat concrete.
  4. Read per-pile first. It is the sanity check: a 12 in pile 10 ft deep should be about 0.29 yd³; if the group total doesn't divide back to that, a count is off.

How the result is calculated

Straight shaft: π × (diameter ÷ 2)² × length. With an under-ream, the shaft length runs to the top of the bell and the bell itself is a frustum: π × height ÷ 3 × (R² + R·r + r²), where R is the bell radius and r the shaft radius. Both × pile count × waste factor; 1 yd³ = 27 ft³. Bag counts use standard US yields (80 lb ≈ 0.60 ft³) — although real pile work is a ready-mix or tremie pour.

Choosing the right numbers

Piles carry load two ways — skin friction along the shaft and end bearing at the bottom — which is why diameter and depth matter more than grade of concrete for volume planning. Per 10 ft of depth, straight shafts:

Shaft diameterConcrete per 10 ft
8 in≈ 0.13 yd³
12 in≈ 0.29 yd³
16 in≈ 0.52 yd³
18 in≈ 0.66 yd³

A bell can double or triple a pile's volume while roughly tripling its end-bearing area — useful in soft clays where depth alone can't find competent soil. Pile sizing, bell geometry and concrete grade are geotechnical outputs: this tool prices the design, it doesn't make it.

Common mistakes to avoid

  • Running shaft length through the bell. The straight section stops at the bell's top; running it to the toe double-counts the frustum's core.
  • Starving the waste factor in wet holes. Water and sloughing over-ream the bore; a dry 10% hole and a wet one can differ by real yards.
  • Assuming the drilled diameter is the named diameter. Augers wander and bells over-ream; log the actual bores and keep waste honest.
  • Counting piles from the layout, not the drill log. Refusals and re-drills change the count — reconcile the log before the plant ticket is written.

Worked examples

Example — 12 piles, 12 in × 12 ft straight shafts, 10% waste

Each = π × 0.5² × 12 ≈ 9.42 ft³ → group ≈ 113.1 ft³; with waste ≈ 124.4 ft³ ≈ 4.61 yd³.

Example — 4 piles, 12 in × 10 ft with 24 in × 18 in bells

Shaft each = π × 0.5² × 10 ≈ 7.85 ft³. Bell (frustum, R = 1 ft, r = 0.5 ft, h = 1.5 ft) ≈ (π × 1.5 ÷ 3) × (1 + 0.5 + 0.25) ≈ 2.75 ft³. Four piles ≈ 42.4 ft³; with 10% waste ≈ 46.7 ft³ ≈ 1.73 yd³.

Frequently asked questions

How much concrete is in a 12 inch pile?

Per foot of depth, π × 0.5² × 1 ≈ 0.785 ft³ ≈ 0.029 yd³. A 10 ft pile is about 0.29 yd³; a 12 ft pile about 0.35 yd³ — roughly 13–14 bags of 80 lb mix per pile if you were bagging (which, for real pile work, you wouldn't).

What is a belled pile?

A bored pile whose bottom is under-reamed into a wider "bell" — often 2–3× the shaft diameter — so the load spreads over far more soil at the base. The bell is a frustum; this calculator computes its volume from the bell diameter and vertical height you enter.

Why is pile waste higher than slab waste?

Bored holes over-pour: sides cave, water displaces, and the actual bore is rarely the nominal diameter. 10% is a fair planning number for wet or unstable holes; dry, cased holes run closer to 5%.

Assumptions, sources and limits

  • Cylindrical shafts of the nominal drilled diameter and frustum bells of the entered geometry; no allowance for casing, tremie pipes or slurry displacement beyond the waste factor.
  • Bag yields use standard US figures (80 lb ≈ 0.60 ft³); pile pours are ready-mix work in practice.
  • Bell volume assumes the under-ream is fully formed as designed — caving or partial bells change the pour reality.
  • Prices come only from your own input.

Planning estimates for pricing an existing design. Pile diameter, depth, bell geometry and concrete specification come from a geotechnical design — never from a volume calculator.