Concrete Stem Wall Calculator

Quote the two pours a stem wall foundation needs — the footing and the wall above it — separately and combined, so the order matches how the work is actually scheduled.

LengthHeightThickness
Please check this value.
Please check this value.
Please check this value.
Please check this value.
Please check this value.
Please check this value.
Feet on center along the sill. Please check this value.
Please check this value.

How to use this tool

  1. Measure the total run along the wall centerline, around every segment of the foundation.
  2. Wall height is what sits on the footing — from footing top to sill. Keep the 16 in default for a typical slab-adjacent stem wall; crawlspace stem walls run taller.
  3. Keep the footing at 16 in × 8 in unless the drawings differ — that pairing is the everyday residential stem-wall footing.
  4. Read the two volumes separately. The footing pour and the wall pour happen days apart, so the plant orders and the crew checks both lines.

How the result is calculated

Two rectangular volumes on the same centerline run: footing = length × footing width × footing thickness and wall = length × wall thickness × wall height, each × your waste factor, ÷ 27 for cubic yards. The footing and wall are poured at different times, which is why they are quoted separately as well as together.

Choosing the right numbers

A stem wall is the hybrid foundation: a continuous footing at the bottom, a short concrete wall on top of it, and either a slab poured inside or a crawlspace floor. It is the go-to on sloped lots, where the stem height steps to follow grade, and wherever the floor needs to sit above the surrounding ground. Per 100 ft of run:

AssemblyConcrete per 100 ft
16×8 footing alone≈ 3.3 yd³
6 in wall × 16 in tall≈ 2.5 yd³
6 in wall × 24 in tall≈ 3.7 yd³
Full assembly (footing + 16 in wall)≈ 5.8 yd³

Two pours, one schedule: the footing cures first (usually with the vertical rebar doweled in), forms for the wall go up on it, then the wall pour. Anchor bolts are set in the wet wall top or drilled after — the spacing you enter orders the count.

Common mistakes to avoid

  • Adding the wall height onto the footing thickness. Height runs from the footing's top; overlap double-counts the joint.
  • One order for both pours. The footing is poured first and the wall days later — if the order arrives combined, someone is paying for a return trip.
  • Stepping heights without re-running the numbers. On a slope, the stem rises in steps; run the tool per segment and add them, or use the average and a slightly fatter waste factor.
  • Ignoring the anchor bolts until the wall is up. Wet-set bolts are the easy path; drilling cured concrete 120 ft of sill later is not.

Worked examples

Example — 40 × 30 ft slab-adjacent stem wall, 16 in tall, 6 in wall on 16×8 footing

Run = 140 ft. Wall = 140 × 1.333 × 0.5 ≈ 93.3 ft³; footing = 140 × 1.333 × 0.667 ≈ 124.4 ft³. With 5% waste ≈ 228.7 ft³ ≈ 8.47 yd³ total — 2.7 yd³ of wall, 5.8 yd³ of footing.

Example — crawlspace stem wall, 24 in tall, 80 ft run

Wall = 80 × 2 × 0.5 = 80 ft³; footing = 80 × 1.333 × 0.667 ≈ 71.1 ft³. With waste ≈ 158.6 ft³ ≈ 5.87 yd³.

Frequently asked questions

What is a stem wall foundation?

A footing at the bottom, a short concrete wall (the "stem") on top of it, and then a slab inside or a crawlspace floor between the walls. It combines the spreading job of a footing with a raised, level platform — the standard choice on sloped lots and where the floor sits above grade.

How tall should a stem wall be?

Commonly 12–24 in above the footing for slab-perimeter use, and taller for crawlspace access — 24–48 in — depending on the crawlspace design. On slopes the height steps with grade.

Are the footing and wall one pour?

Usually not. The footing cures first with dowels left projecting, then the wall forms go up and the wall is poured on top. That is why this calculator quotes the two volumes separately as well as together.

Assumptions, sources and limits

  • Prismatic walls and footings of uniform section on the same centerline; stepped foundations need per-segment runs.
  • Bag yields use standard US figures (80 lb ≈ 0.60 ft³, 60 lb ≈ 0.45 ft³); stem-wall pours are ready-mix work in practice.
  • Anchor bolt count is a length ÷ spacing + 1 order estimate.
  • Prices come only from your own input.

Planning estimates only. Stem wall height, footing size and reinforcement must follow your local code and the engineered drawings.