How to use this tool
- Measure the length and average exposed height. On sloped ground the wall steps; average the exposed face, then let the waste factor absorb the uneven part.
- Set the stem thickness. Keep 8 in at the top; poured walls commonly thicken toward the base — enter that bottom thickness and the tool averages the taper.
- Keep the footing at the 16 in × 8 in default for low walls. Walls over about 4 ft exposed stop being rule-of-thumb jobs.
- Keep the drain gravel at 12 in. Hydrostatic pressure behind a wall without drainage is what actually breaks walls — the gravel chimney and weep holes are not decorations.
How the result is calculated
Stem = length × height × average thickness — the average of the top and bottom thicknesses handles the taper most poured walls have. Footing = length × footing width × footing thickness. Both × your waste factor, ÷ 27 for cubic yards. Drainage gravel = length × height × gravel width behind the wall, quoted separately because it is a different material order.
Choosing the right numbers
Poured retaining walls fail by water and by tipping, not by concrete strength. The design logic is a heavier, wider base that resists overturning, gravel and weep holes that keep water from ever building up, and reinforcement sized to the wall's height. For preliminary material planning on low walls:
| Exposed height | Stem | Footing | Concrete per 10 ft |
|---|---|---|---|
| 2 ft | 6 in | 12 in × 6 in | ≈ 0.30 yd³ |
| 3 ft | 8 in | 16 in × 8 in | ≈ 0.50 yd³ |
| 4 ft | 8–10 in, thickened base | 20 in × 10 in | ≈ 0.75 yd³ |
Above roughly 4 ft exposed — or with a slope, a structure, or vehicle loading behind the wall — the wall becomes an engineered design: footing width, toe/heel proportions, rebar schedule and drainage all come from the drawings, not from a table.
Common mistakes to avoid
- Skipping the drainage gravel to save money. It is the cheapest line on the job and the failure mode it prevents is the expensive one. Gravel plus weep holes keep the wall holding soil, not water.
- Measuring height from footing bottom. Enter the average exposed height for planning; the buried portion of the stem belongs in the taper and waste allowance.
- Building on fill or loose soil. The footing bears on what is under it; retaining walls on uncompacted fill settle and crack in their first wet season.
- No rebar. A poured retaining wall is a bending element — unreinforced walls crack along their length the first winter.
- Ordering gravel in "wall cubic yards." The gravel line is its own volume and its own delivery; the tool quotes it separately for that reason.
Worked examples
Example — 20 ft terrace wall, 3 ft exposed, 8 in stem, 16×8 footing, 12 in drain gravel
Stem = 20 × 3 × 0.667 ≈ 40 ft³; footing = 20 × 1.333 × 0.667 ≈ 17.8 ft³. Concrete with 5% waste ≈ 60.8 ft³ ≈ 2.25 yd³. Gravel = 20 × 3 × 1 = 60 ft³ ≈ 2.22 yd³.
Example — 24 ft driveway wall, 4 ft exposed, 8→12 in tapered stem, 20×10 footing
Average stem thickness = 10 in ≈ 0.833 ft → stem = 24 × 4 × 0.833 ≈ 80 ft³; footing = 24 × 1.667 × 0.833 ≈ 33.3 ft³. With waste ≈ 4.27 yd³ of concrete, plus ≈ 4.44 yd³ of drain gravel.
Frequently asked questions
How much concrete for a 3 ft retaining wall?
Per 10 ft of length: about 0.5 yd³ (stem plus footing) for an 8 in stem on a 16×8 footing. A 20 ft terrace wall like the example above lands around 2.2–2.3 yd³ with waste.
Why does a retaining wall need gravel behind it?
Water pressure behind a wall can be several times the pressure from the soil itself. A washed-gravel chimney with weep holes drains that water away before it loads the wall — it is the single cheapest way to keep a wall standing.
How thick should a poured retaining wall be?
Low landscape walls: 6–8 in stems on proportionally wider footings. At 4 ft and beyond the stem thickens toward the base and the design is engineered — thickness alone stops being the deciding factor.
Assumptions, sources and limits
- Straight walls of uniform or linearly tapered section; stepped walls and curves need per-segment runs.
- The exposed height you enter approximates the full stem height for volume purposes; buried stem depth should be added to the taper allowance.
- Drain gravel is quoted as a clean chimney of the entered width, full height, behind the stem — excavated native soil volume is not included.
- The size table is for light, low, landscape-scale walls only. Anything over ~4 ft, or carrying structures or vehicles, is an engineered design.
- Prices come only from your own input.
Planning estimates for low landscape walls. Taller or loaded retaining walls require a qualified engineer's design.