How to use this tool
- Enter the pour size — the labor-per-yard math only makes sense against real volume.
- Size the crew and the day. Flat work: 3–4 people for most residential pours. Footings: 2–3. Big slabs: 5+ or a pump crew.
- Use the loaded rate. A $30/hr worker costs a crew leader ~$45–55/hr once taxes, insurance and workers' comp land.
- Add equipment. Power trowel, mixer, compactor — most pours have a rental line.
How the result is calculated
Labor = crew size × hours × loaded hourly rate. Add the day's equipment rental for the true site cost. The benchmarks that matter: a practiced 3–4 person crew places and finishes roughly 1–1.5 yd³ per hour on flat work in good conditions, and small pours carry fixed overhead (setup, forms, cleanup) that has nothing to do with volume — which is why labor per yard falls fast as pours grow.
Choosing the right numbers
How long pours actually take, for a competent residential crew (place, screed, bull-float, finish):
| Pour | Crew | Typical site time | Labor at 3 × $45 |
|---|---|---|---|
| Patio 10×12 ft | 3 | 5–7 h (with forms) | $675–945 |
| Driveway 20×20 ft | 4 | 7–9 h | $1,260–1,620 |
| Garage 24×24 ft | 4–5 | 8–10 h | $1,620–2,250 |
| Footing run 60 ft | 2–3 | 4–6 h | $270–810 |
What the hours contain: forms and base prep often take longer than the pour itself; finishing is weather-dependent (hot days shorten the window and raise the crew count); and cleanup is always there. Labor per yard on a small pad can exceed the concrete's own cost — on a driveway it's usually 1–1.5× material.
Common mistakes to avoid
- Pricing labor at the wage, not the loaded rate. Taxes, comp and insurance add 25–45% — quotes built on raw wages lose money.
- Ignoring form time. The pour is hours; the forms are the day before. If your estimate starts when the truck arrives, it's half an estimate.
- Same crew size for every job. Hot-weather finishing is a crew-count problem — concrete sets when it wants, and a short crew loses the window.
- Skipping the equipment line. A power trowel rental is small money that changes the finish and the schedule.
- Forgetting cleanup and return trips. Saw cuts the next day, form stripping, backfill — labor that shows up after the truck leaves.
Worked examples
Example — 5 yd³ patio, 3 crew × 7 h × $45, $180 equipment
Labor = $945; with equipment $1,125 — $225/yd³ labor, about 4.2 man-hours per yard.
Example — same crew on a 20 yd³ driveway, 4 × 9 h
4 × 9 × 45 = $1,620 + $220 rental = $1,840 — but only $92/yd³. Volume is what amortizes labor.
Frequently asked questions
How much does concrete labor cost per yard?
On residential flat work, commonly $80–200 per cubic yard depending on job size and finish — small pours run higher because setup and cleanup don't scale. Enter your crew and rate above for your number.
How many people does it take to pour concrete?
A 3–4 person crew handles most residential flat work: one on the chute/screed, one screeding and bull-floating, one finishing and managing the pour. Hot days and big slabs add hands; footing pours can run leaner.
What does "loaded labor rate" mean?
The full cost of an hour of a worker: wage plus payroll taxes, workers' comp, insurance and benefits — typically 1.25–1.45× the paycheck. Quotes built on the raw wage underprice the job.
Assumptions, sources and limits
- Loaded hourly rate is your input — the tool does not guess local wages or burden percentages.
- Hours are total site time including forms, pour, finish and cleanup as you define them.
- Productivity benchmarks (1–1.5 yd³/man-hour crew output on flat work) are broad practice observations; conditions, access and finish level move them.
- Does not include specialized work: pumping, stamping crews, saw-cutting subcontractors.
Planning estimates. Real bids reflect the contractor's actual crew, market and margin.