How to use this tool
- Enter the order and the plant's base price.
- Add the fixed fees from the quote — delivery is per order, fuel surcharge as a percentage if they quote one.
- Enter the stand-by rate if the quote lists one — most plants do, around $85–150/hour per truck.
- Stress-test with a delay. Enter the minutes your pour might overrun; the risk line is what a slow afternoon costs.
How the result is calculated
Delivered cost = concrete (yards × price) + delivery fee + fuel surcharge + stand-by charges. Fuel surcharge is a percentage of the material bill. Stand-by: plants typically allow about 10 minutes of unload time per yard; time beyond it bills at the per-truck hourly rate. The "risk" line adds your possible delay at that rate — the number to know before the pour, not during it.
Choosing the right numbers
What the transportation side of a ticket actually contains:
| Line | Typical shape | When it bites |
|---|---|---|
| Delivery fee | $50–120 per order | Always — hurts small orders most |
| Fuel surcharge | 0–8% of the bill | When diesel spikes; ask if folded in |
| Stand-by | $85–150/hr per truck after ~10 min/yd free | Slow chutes, understaffed crews, long pumps |
| Small-load fee | $50–150 or billed minimum | Orders under ~4 yd³ |
| After-hours / weekend | $10–25/yd³ extra | Early, late or Sunday pours |
The stand-by line is the one crews underestimate. A pump moves concrete in 2–4 minutes per yard; a three-man wheelbarrow crew on a long run can take 15 — on a 6-yard pour that is an hour over free time, and the meter runs.
Common mistakes to avoid
- Budgeting only the material line. Delivery, fuel and risk together commonly add 15–30% to a small order's bill.
- Not asking if fuel is folded in. Some plants quote "delivered price"; others add surcharge at invoice — the gap shows up on the ticket.
- Understaffing the pour. Stand-by charges are bought by the hour and sold by the minute — an extra chute hand is cheaper than two hours of truck time.
- No pump decision. At 15+ minutes per yard of chute labor, a pump rental usually pays for itself on pours over ~5 yards.
- Scheduling the truck before the site is ready. Forms, base, access and crew all cost money while the mixer idles at the gate.
Worked examples
Example — 6 yd³ at $165, $75 delivery, 3% fuel, $100/hr stand-by
Material $990 + fees $104.70 = $1,094.70 expected. At 10 min/yd you're at the free-time edge; a 30-minute overrun adds $50 risk → $1,144.70 worst case, $183/yd³.
Example — 3 yd³ small order, same terms
Material $495 + fees $89.85 = $584.85 — $195/yd³ effective. The fixed $75 rides only 3 yards; that's the small-order penalty in one line.
Frequently asked questions
How much is concrete delivery?
Typically $50–120 per order on top of the concrete, plus possible fuel surcharges and small-load fees. On a 5-yard order that adds roughly $2–5 per yard; on a 1-yard order it can double the bill.
What is a concrete stand-by charge?
The plant's clock on your unload time: after the free allowance (~10 minutes per yard), the truck bills at an hourly rate — often $85–150/hour. Slow crews pay it; fast crews never see it.
Do I need to worry about fuel surcharges?
Ask when quoting. They appear when diesel spikes, usually 2–8% of the bill, and some plants fold them into the quoted price permanently.
Assumptions, sources and limits
- Free unload time modeled at 10 min/yd — your plant's terms govern.
- Stand-by modeled as a single blended hourly rate; multi-truck pours bill per truck and the real meter is messier.
- Fuel surcharge applies to the material bill; some plants apply it to the whole ticket.
- All rates come only from your own input.
Cost-planning tool. The plant's written quote — including its stand-by language — is the binding one.