How to use this tool
- Build the four direct lines from your own math — the volume, labor and material tools upstream produce each one.
- Set markup honestly. It carries your insurance, truck, admin and the winter you don't work — 20% is the honest default for small operations.
- Add tax where your state requires it on contractor work.
- Name the scope precisely. The scope line is the bid's legal spine — thickness, reinforcement, finish, exclusions.
- Copy the proposal text and paste it into your email — the numbers and the terms travel together.
How the result is calculated
Bid total = direct costs × (1 + markup %) × (1 + tax %). Direct costs are your four lines: concrete (yards × price), labor (man-hours × loaded rate), equipment and other materials. Markup carries overhead and profit — 15–25% is the common small-contractor band; under 10% is working for free once overhead lands. The proposal text assembles the same numbers in client-ready form, and the copy button grabs it whole.
Choosing the right numbers
What separates a professional bid from a number on a napkin:
| Element | Why it earns its line |
|---|---|
| Quantified scope | Thickness, reinforcement, finish, footprint — the four things that change the price |
| Separate material & labor | Lets the client see the work; lets you defend the price |
| Visible markup | Hidden markup looks like padding; stated overhead reads as professionalism |
| Exclusions | Permits, demolition, grading below grade — say what's NOT in it |
| Terms & validity | Payment schedule and a 30-day clock protect both sides |
Markup discipline: overhead is real — insurance, truck, tools, office time, the slow season. A crew that bids at cost-plus-zero is a crew that folds the first time equipment breaks. The band varies by market; the error is not having a band at all.
Common mistakes to avoid
- Bidding from raw wages. Unloaded labor rates quietly erase profit — use loaded rates in the man-hour line.
- Vague scope. "Concrete driveway" invites the client to expect 6 in with rebar when you priced 4 in plain. Quantify or absorb the dispute.
- No exclusions. Permits, demolition, and subgrade repair are the three classic scope-creep sources — exclude them in writing.
- Markup under 10%. Once overhead, warranty callbacks and the unpaid estimating hours land, that margin is negative.
- No validity window. Concrete prices move; a bid without a clock is an option you sold for free.
Worked examples
Example — the driveway bid
Direct: $1,223 concrete + $1,440 labor + $180 equipment + $570 materials = $3,413. Markup 20% = $683. Tax 7% = $287. Bid total $4,383 ($592/yd³ effective) — and the proposal text renders the whole sheet, ready to send.
Example — small pad bid
1.6 yd³ @ $165 + 16 man-hours @ $45 + $120 equipment + $180 materials = $944 direct; 20% markup + 7% tax → $1,212. Small jobs look expensive per yard because their fixed lines are not negotiable — the proposal shows why, line by line.
Frequently asked questions
What markup should a concrete contractor charge?
Small residential contractors commonly run 15–25% on direct costs to cover overhead and profit. Below 15% rarely survives a season of real overhead; the right number reflects your insurance, equipment and admin load.
How do I write a concrete bid?
Quantified scope, line-item costs (material and labor separately), stated markup, exclusions in writing, payment terms and a validity window. The generator above assembles exactly that and copies it out as text.
Should labor and materials be separate lines?
Yes — it makes the bid defensible and comparable, and it protects you when the client asks why the price is what it is. A single number invites suspicion; a breakdown invites respect.
Assumptions, sources and limits
- All quantities, rates and percentages are your inputs; the tool assembles and formats — it does not market-price anything.
- Markup applies to direct costs; tax applies to the markup-adjusted subtotal. Some jurisdictions tax differently — set the rate to match your rules.
- The generated proposal text is a template for professional communication, not legal advice; contract language belongs to your contract.
- Warranty and payment terms in the template are common defaults — edit them to your actual terms.
A bid-sheet builder. Pricing judgment, contracts and local tax rules remain yours.