Cubic Feet ⇄ Cubic Yards Converter

The one conversion every concrete order crosses: feet for measuring, yards for ordering. Enter either side and get both, plus cubic meters.

Please check this value.
Please check this value.

How to use this tool

  1. Pick the direction — feet to yards when you've measured a pour and need an order size; yards to feet when a delivery amount needs to make sense against your footprint.
  2. Type the value. The answer updates live, with cubic meters alongside for metric drawings or suppliers.

How the result is calculated

1 cubic yard = 27 cubic feet — a yard measures 3 ft on each side, so 3 × 3 × 3 = 27. Conversions: cubic feet ÷ 27 → yards; cubic yards × 27 → feet. For metric: 1 yd³ ≈ 0.7646 m³ and 1 ft³ ≈ 0.0283 m³. That is the entire rule — every other "yard math" mystery in concrete work reduces to it.

Choosing the right numbers

Landmark conversions worth memorizing for concrete work:

Cubic feetCubic yardsRoughly
1 ft³0.037 yd³One 80 lb bag's yield ≈ 0.6 ft³
13.5 ft³0.5 yd³Half-yard short loads
27 ft³1 yd³81 ft² at 4 in thick
40.5 ft³1.5 yd³Typical shed floor
54 ft³2 yd³Small patio
81 ft³3 yd³One-car driveway pad

Why the units split the way they do: your tape measure speaks feet, the plant's batch ticket speaks yards, and bags speak pounds. The 27 rule is the bridge between all three — and the most common estimating error in concrete work is forgetting it at the boundary (measuring in feet, ordering in yards, without dividing by 27).

Common mistakes to avoid

  • Dividing by 9. Nine converts square feet to square yards — area. Volume needs 27. Mixing the two rules is the classic order-size error.
  • Converting the wrong side of a mixed expression. If thickness is in inches and footprint in feet, convert inches to feet (÷ 12) first, then multiply — then divide by 27 at the very end.
  • Rounding mid-chain. Keep full precision through the multiplication, round once at the end — especially on small pours where 0.01 yd³ matters.
  • Trusting rounded conversions for orders. 0.29 yd³ calculated means ordering 0.25 or 0.5 from the plant — batch steps are quarter-yard, not continuous.

Worked examples

Example — measured 148.5 ft³

148.5 ÷ 27 = 5.5 yd³ — with 10% waste in the original number, that is the plant order.

Example — the plant delivers 4.75 yd³

4.75 × 27 = 128.25 ft³ — spread over a 4 in pour, that is 385 ft² of coverage.

Frequently asked questions

How many cubic feet are in a cubic yard?

27. A yard is 3 feet, so a cubic yard is 3 × 3 × 3 = 27 cubic feet. Multiply yards by 27; divide feet by 27.

Is 9 the conversion for volume too?

No — 9 converts square feet to square yards (area). Volume is 27. If your order is off by a factor of three, this is usually why.

How many cubic yards is 100 cubic feet?

100 ÷ 27 ≈ 3.70 yd³. At 4 in thick, 100 ft³ covers 300 ft².

Assumptions, sources and limits

  • Pure unit conversion — no waste factors, no batch rounding; apply those at the order stage.
  • Metric factors: 1 ft³ = 0.0283168 m³, 1 yd³ = 0.764555 m³ (both exact by definition of the inch).

A math utility — everything else about the order is a different tool.