How to use this tool
- Enter the order size — your calculated yards after the waste factor, rounded up to the plant's quarter-yard batch step.
- Pick the truck size the plant actually runs; most US mixers max out around 10–11 yd³, and local roads or site access can cap them lower.
- Keep 10 min/yd unless your crew has proven faster or the pour has a pump (pumps move 1 yd³ in 2–4 minutes).
- Read the part load. A 0.8 yd³ tail on a 3-truck order often costs a short-load fee — ask the plant about splitting or adding to it.
How the result is calculated
Trucks = total yards ÷ truck capacity, rounded up. Full loads carry the capacity evenly; the remainder rides a part load — which many plants charge extra for or batch last. Chute time multiplies your yards by the unloading rate; 10 minutes per yard is a common planning figure, and plants start charging stand-by fees when their trucks wait on you beyond it.
Choosing the right numbers
What typical orders look like on 10 yd³ trucks:
| Order | Trucks | Load plan |
|---|---|---|
| 5 yd³ (patio) | 1 | Half load — fine, some plants charge a part-load fee under ~4 yd³ |
| 10.5 yd³ (small driveway) | 2 | 10 + 0.5 — the 0.5 tail is a classic short-load fee |
| 21 yd³ (garage slab) | 3 | 10 + 10 + 1 |
| 32 yd³ (foundation package) | 4 | 10 + 10 + 10 + 2 |
Two scheduling realities: trucks arrive spaced so their unload windows don't collide — 45–60 min apart for two trucks on a slow chute — and each mixer's load has a clock (roughly 90 minutes from batching before the plant wants it out, and washout begins). Big pours are a choreography problem, not just a volume problem.
Common mistakes to avoid
- Assuming all trucks arrive at once. Plants stagger deliveries; a two-truck pour is a 90-minute rhythm, not one event.
- Ignoring the part-load fee. A 0.3 yd³ tail can cost more per yard than the whole load — talk to the plant about rounding the order or the plan.
- No stand-by plan. If your chute time slips past the plant's allowance, stand-by charges start per minute. A second chute operator or a pump pays for itself on big pours.
- Ordering full trucks to "round up." 23 yd³ of need doesn't become 30 yd³ of order — the extra 7 yards have nowhere to go and get charged anyway.
- Site access unverified. A 10 yd³ mixer weighs ~40 tons loaded; a driveway or gate it can't reach means wheelbarrows, pumps, or a return trip.
Worked examples
Example — 24 yd³ order on 10 yd³ trucks
3 trucks: 10 + 10 + 4. Chute time at 10 min/yd = 240 minutes = 4 hours of continuous unloading — worth pricing a pump.
Example — 11.2 yd³ on 9 yd³ trucks
2 trucks: 9 + 2.2. The 2.2 part load is where the plant's short-load policy matters — sometimes it's cheaper to round the order to 11 or 13.5 than to pay the tail fee.
Frequently asked questions
How many yards fit in a concrete truck?
Most US mixer trucks carry 10–11 yd³ at legal weight; small mixers run 8. The plant will confirm what their fleet and your road can take.
How long does a truck take to unload?
About 10 minutes per yard through the standard chute — a full 10 yd³ load is 100 minutes of gate time. A pump cuts that to 2–4 minutes per yard, which is why big pours rent one.
Why did the plant send my order in two trucks?
Orders above truck capacity are staggered: one truck unloads while the next waits. Plants space arrivals so concrete stays within its batch clock — typically 90 minutes from batching.
What is a part-load fee?
Plants batch and charge minimums — often 4–5 yd³ — because a half-loaded truck costs them almost what a full one does. The odd tail on your order can trigger it; ask when the tail is under that line.
Assumptions, sources and limits
- Truck capacities are the common US mixer sizes; your plant's fleet and local road limits may differ.
- Unloading rate is chute-through-the-gate time; pumping, long chutes and difficult access slow it down.
- Part loads are shown as calculated; plant fees for them are a conversation with the plant, not a formula.
- Prices come only from your own input.
Scheduling estimates only. Confirm loads, fees and timing with your supplier — their batch schedule is the real one.