How to use this tool
- Know your mixer's real output. The drum rating is not it — a "5 cu ft" mixer produces maybe 2 ft³ per batch. The presets encode that.
- Enter the total volume from your pour calculator.
- Pick the ratio for the strength you need.
- Pre-stage your materials. Sand and gravel piles measured into equal buckets before batch one — the schedule has no pause for fetching.
- Keep batches coming. A batch every 6 minutes or so keeps the placed concrete knitting; long gaps show as cold joints.
How the result is calculated
Batches = total volume ÷ working capacity per batch, rounded up. Each batch's ingredients split the dry volume — total × 1.6 for the voids-and-shrink factor — by the mix ratio's parts, exactly like the mix ratio calculator but divided evenly per batch. Cement: sand : gravel ratios: 1:3:4 ≈ 3,000 psi, 1:2.5:3 ≈ 3,500 psi, 1:2:3 ≈ 4,000 psi. A mixer's drum size is not its working capacity — batches run at roughly 60–70% of drum volume or the motor bogs and the mix won't blend.
Choosing the right numbers
What batch work looks like in practice:
| Total pour | Medium mixer (2 ft³/batch) | Batches | Straight advice |
|---|---|---|---|
| 4 ft³ (mailbox pad) | 2 batches | 2 | One afternoon, easy |
| 13.5 ft³ (0.5 yd³, small pad) | — | 7 | Doable with help; rent the mixer |
| 27 ft³ (1 yd³) | — | 14 | 90+ min of continuous mixing — the crossover |
| 40+ ft³ | — | 20+ | Order the truck. Really. |
Batch discipline that separates clean pours from lumpy ones: identical measured parts every batch (a spare bucket as the "cement bucket" lives its whole life as the cement bucket), water metered not splashed, and a helper placing and screeding behind the mixer so each batch lands into wet edge, not hardened edge.
Common mistakes to avoid
- Trusting the drum rating. Overfilled mixers don't tumble — they fold, leaving unmixed pockets of dry sand.
- Varying batches. Batch 1 measured, batch 9 eyeballed — the slab shows every compromise as blotches and weak spots.
- No water discipline. Loose water at the end to "make it flow" rewrites the w/c ratio batch by batch.
- Letting the mixer stop. Two batches an hour is not a pour; it's three cold joints waiting to crack.
- Mixing day with no helper. One person mixing and placing alone runs batches 9–10 minutes apart — too slow for anything bigger than a pad.
Worked examples
Example — 13.5 ft³ (0.5 yd³) at 3,500 psi, medium mixer
7 batches. Dry per batch ≈ 3.09 ft³ → cement ≈ 0.48 ft³ (45 lb, half a bag), sand ≈ 1.19 ft³, gravel ≈ 1.42 ft³, water ≈ 2.7 gal per batch. Total: 4 bags of cement, ~19 gal water.
Example — 2 ft³ custom batches for a 8 ft³ pour
4 batches, each ≈ 3.2 ft³ dry split by 1:2.5:3 → half-bag, ~1.2 ft³ sand, ~1.5 ft³ gravel each.
Frequently asked questions
How much concrete can a mixer do per batch?
Roughly 60–70% of the drum rating: a common 5 cu ft drum yields about 2 ft³ of mixed concrete per batch — one third of a bag of cement's worth of finished material. The presets above encode the common sizes.
How long does it take to mix a yard of concrete by hand?
With a medium mixer at ~2 ft³ per batch: about 14 batches and 90–120 minutes of continuous work with a helper. That is exactly why one cubic yard is the crossover to ready-mix delivery.
How do I keep bagged batches consistent?
Same bucket for every part, water metered to the same level, and a fixed mixing time per batch. Variability between batches shows up in the slab as blotches and weak zones — the discipline is the recipe.
Assumptions, sources and limits
- Mixer presets encode common working capacities at ~60–70% of drum rating; your machine's manual wins.
- Dry-volume factor 1.6, cement 94 lb/ft³, w/c 0.50 — same estimating figures as the mix ratio tool.
- Batch cycle estimate (~6 min: load, mix, place, reload) is a planning figure; novice cycles run longer.
- Ingredient totals round for practicality — keep the spare-bucket method for consistency.
Batch planning for site mixing. Code-governed pours belong on a plant's batch ticket.