Concrete Batch Calculator

One mixer, many batches. Enter the total pour and your mixer's working capacity, and get the batch count plus each batch's exact ingredient split.

Please check this value.
Please check this value.
Please check this value.
Please check this value.

How to use this tool

  1. Know your mixer's real output. The drum rating is not it — a "5 cu ft" mixer produces maybe 2 ft³ per batch. The presets encode that.
  2. Enter the total volume from your pour calculator.
  3. Pick the ratio for the strength you need.
  4. Pre-stage your materials. Sand and gravel piles measured into equal buckets before batch one — the schedule has no pause for fetching.
  5. Keep batches coming. A batch every 6 minutes or so keeps the placed concrete knitting; long gaps show as cold joints.

How the result is calculated

Batches = total volume ÷ working capacity per batch, rounded up. Each batch's ingredients split the dry volume — total × 1.6 for the voids-and-shrink factor — by the mix ratio's parts, exactly like the mix ratio calculator but divided evenly per batch. Cement: sand : gravel ratios: 1:3:4 ≈ 3,000 psi, 1:2.5:3 ≈ 3,500 psi, 1:2:3 ≈ 4,000 psi. A mixer's drum size is not its working capacity — batches run at roughly 60–70% of drum volume or the motor bogs and the mix won't blend.

Choosing the right numbers

What batch work looks like in practice:

Total pourMedium mixer (2 ft³/batch)BatchesStraight advice
4 ft³ (mailbox pad)2 batches2One afternoon, easy
13.5 ft³ (0.5 yd³, small pad)—7Doable with help; rent the mixer
27 ft³ (1 yd³)—1490+ min of continuous mixing — the crossover
40+ ft³—20+Order the truck. Really.

Batch discipline that separates clean pours from lumpy ones: identical measured parts every batch (a spare bucket as the "cement bucket" lives its whole life as the cement bucket), water metered not splashed, and a helper placing and screeding behind the mixer so each batch lands into wet edge, not hardened edge.

Common mistakes to avoid

  • Trusting the drum rating. Overfilled mixers don't tumble — they fold, leaving unmixed pockets of dry sand.
  • Varying batches. Batch 1 measured, batch 9 eyeballed — the slab shows every compromise as blotches and weak spots.
  • No water discipline. Loose water at the end to "make it flow" rewrites the w/c ratio batch by batch.
  • Letting the mixer stop. Two batches an hour is not a pour; it's three cold joints waiting to crack.
  • Mixing day with no helper. One person mixing and placing alone runs batches 9–10 minutes apart — too slow for anything bigger than a pad.

Worked examples

Example — 13.5 ft³ (0.5 yd³) at 3,500 psi, medium mixer

7 batches. Dry per batch ≈ 3.09 ft³ → cement ≈ 0.48 ft³ (45 lb, half a bag), sand ≈ 1.19 ft³, gravel ≈ 1.42 ft³, water ≈ 2.7 gal per batch. Total: 4 bags of cement, ~19 gal water.

Example — 2 ft³ custom batches for a 8 ft³ pour

4 batches, each ≈ 3.2 ft³ dry split by 1:2.5:3 → half-bag, ~1.2 ft³ sand, ~1.5 ft³ gravel each.

Frequently asked questions

How much concrete can a mixer do per batch?

Roughly 60–70% of the drum rating: a common 5 cu ft drum yields about 2 ft³ of mixed concrete per batch — one third of a bag of cement's worth of finished material. The presets above encode the common sizes.

How long does it take to mix a yard of concrete by hand?

With a medium mixer at ~2 ft³ per batch: about 14 batches and 90–120 minutes of continuous work with a helper. That is exactly why one cubic yard is the crossover to ready-mix delivery.

How do I keep bagged batches consistent?

Same bucket for every part, water metered to the same level, and a fixed mixing time per batch. Variability between batches shows up in the slab as blotches and weak zones — the discipline is the recipe.

Assumptions, sources and limits

  • Mixer presets encode common working capacities at ~60–70% of drum rating; your machine's manual wins.
  • Dry-volume factor 1.6, cement 94 lb/ft³, w/c 0.50 — same estimating figures as the mix ratio tool.
  • Batch cycle estimate (~6 min: load, mix, place, reload) is a planning figure; novice cycles run longer.
  • Ingredient totals round for practicality — keep the spare-bucket method for consistency.

Batch planning for site mixing. Code-governed pours belong on a plant's batch ticket.