Cement Quantity Calculator

How many bags of straight portland cement does your pour need? Enter the volume and the mix ratio — get the bag count, the sand and gravel alongside, and the cement cost.

Please check this value.
Please check this value.
Please check this value.
Please check this value.

How to use this tool

  1. Enter the finished volume — from your pour calculator, waste included.
  2. Pick the ratio that matches the job's strength demand. Stronger mixes spend more cement per yard — that is exactly what the strength is made of.
  3. Order by the bag. The count rounds up; partial bags keep poorly once opened, so the round-up is also the spares.
  4. Check the per-yard context line — 5–7 bags per yard is the normal band; wildly outside it means the ratio or the volume is off.

How the result is calculated

From the mix ratio: cement volume = dry volume × (cement parts ÷ total parts), where dry volume ≈ 1.6 × finished volume. Loose portland cement weighs ≈ 94 lb per ft³ — one bag. So a 1:2.5:3 mix (6.5 parts) puts one part of six and a half into cement: a cubic yard (27 ft³) takes 43.2 dry ft³ × 1/6.5 ≈ 6.65 ft³ ≈ 624 lb ≈ 6.6 bags of cement per yard, with sand and gravel making up the rest.

Choosing the right numbers

Cement spending by mix, per finished cubic yard:

MixCement per yd³Bags (94 lb)
1 : 3 : 4 (≈3,000 psi)≈ 515 lb≈ 5.5
1 : 2.5 : 3 (≈3,500 psi)≈ 624 lb≈ 6.6
1 : 2 : 3 (≈4,000 psi)≈ 677 lb≈ 7.2
1 : 1.7 : 2.6 (≈4,500 psi)≈ 733 lb≈ 7.8

For orientation: ready-mix plants batch 5–6.5 bags (470–610 lb) per yard for common residential mixes — the site-ratio method spends slightly more cement for similar strength, which is part of why bag-mixed concrete rarely beats the truck on cost past the crossover.

Common mistakes to avoid

  • Buying "concrete mix" bags for this math. Those are pre-blended — cement, sand and gravel together. This calculator is for straight portland cement plus your own aggregates.
  • Counting a bag as a cubic foot of concrete. One 94 lb bag of cement is one ingredient measure; it helps make roughly 1.4 ft³ of concrete in a 1:2:3 mix.
  • Storing bags outdoors. Cement draws moisture and cements itself into a rock in weeks. Buy close to pour day, store dry and off the ground.
  • Skipping the aggregate weights. Cement is the expensive small line; sand and gravel are the cheap bulk lines — the tool totals both so the quarry run is planned.

Worked examples

Example — 0.5 yd³ of 3,500 psi mix

Dry = 21.6 ft³; cement = 21.6 ÷ 6.5 ≈ 3.32 ft³ ≈ 312 lb → 4 bags (3.3 needed, round up). Sand ≈ 8.3 ft³ ≈ 0.41 tons; gravel ≈ 10 ft³ ≈ 0.49 tons.

Example — 1 yd³ at 4,000 psi with $14 bags

≈ 677 lb → 8 bags = $112, plus ~0.42 tons of sand and ~0.5 tons of gravel from the yard.

Frequently asked questions

How many bags of cement make a yard of concrete?

About 5.5 bags for a lean 1:3:4 mix, ~6.6 for 1:2.5:3, and ~7–8 bags for 4,000+ psi mixes — measured in 94 lb bags of straight portland cement, with sand and gravel making up the rest.

How much does a bag of cement yield in concrete?

One 94 lb bag in a 1:2:3 mix contributes to roughly 1.4 ft³ of finished concrete (with its sand and gravel companions). Cement alone is never the yield — the batch is.

Is bagged cement cheaper than ready-mix?

The cement line alone looks cheap, but add sand, gravel, hauling and your mixing labor and the crossover sits around a yard — past it, ready-mix usually wins on both cost and consistency.

Assumptions, sources and limits

  • Standard US bag: 94 lb of loose portland cement ≈ 1 ft³.
  • Dry-volume factor 1.6; aggregate densities (~100 lb/ft³ sand, ~105 lb/ft³ gravel) are bulk estimating figures — your supplier's moisture and grading vary.
  • Ratio-to-strength labels are the traditional approximations; verified strength requires a mix design and testing.
  • Prices come only from your own input.

Material planning for site mixing. Plant batches carry their own cement content on the ticket.