How to use this tool
- Measure the area and fill depth — for sloped fills, use the average depth and let the waste factor catch the variation.
- Add a generous waste factor: 15–25%. Fill dirt compacts 15–20% when tamped and settles more over time — the loose order must exceed the finished depth.
- Order in lifts. Deep fills are placed and compacted in 6–8 in layers, not dumped at once — the total covers the lifts.
How the result is calculated
Volume = length × width × depth (all in matching units), × count, × your waste factor; 1 yd³ = 27 ft³. Weight = volume × loose density — this tool uses ≈ 110 lb/ft³ for fill dirt, which lands at roughly 1.49 tons per cubic yard. Loose density varies with moisture and grading — quarry tickets and delivery slips are the real weight.
Choosing the right numbers
What fill dirt is — and isn't:
| Material | Compaction | Use |
|---|---|---|
| Common fill / subsoil | Compacts well in lifts | Grading, building up ground, backfill |
| Clean fill (certified) | — | Where contamination documentation matters |
| Sandy fill | Drains, compacts fast | Wet sites, drainage-critical fills |
| Clay fill | Slow, moisture-sensitive | Dams, pads — needs moisture control |
| Topsoil | Never structural fill | The final 4–6 in only, for planting |
The compaction arithmetic everyone forgets: a finished 12 in compacted fill starts as 14–15 in of loose dirt. And the legal one: "clean fill" has a definition — fill with unknown history (demolition debris, dredge spoil) can carry contaminants your municipality regulates. Ask what the load actually is.
Common mistakes to avoid
- Ordering to finished depth. Without the compaction allowance, a 12 in fill finishes at 10 in and the low spot returns.
- Single deep dumps. Uncompacted 3 ft fills settle for years; lifts of 6–8 in with plate compaction settle predictably.
- Fill against foundations without drainage. Dirt held against a wall traps water — gravel zones and drainage fabric belong at those interfaces.
- "Free dirt" without questions. Demolition debris, roots and construction trash rot, settle and smell. Certified clean fill exists for a reason.
- Topsoil as fill. Organic soil compresses and rots — structural fill is mineral soil; topsoil is the last layer only.
Worked examples
Example — 20 × 30 ft low area, average 6 in deep, 20% compaction
600 ft² × 0.5 = 300 ft³ × 1.2 = 360 ft³ ≈ 13.3 yd³ ≈ 19.8 tons — placed in two lifts with a plate compactor.
Example — backfilling a 3 ft trench, 40 ft long × 2 ft wide
240 ft³ × 1.2 = 288 ft³ ≈ 10.7 yd³ ≈ 15.8 tons.
Frequently asked questions
How much does a yard of fill dirt weigh?
About 3,000 lb ≈ 1.5 tons loose at typical moisture — heavier wet, lighter sandy. Scale tickets vary widely; this is a planning figure.
How much does dirt compact?
Loose fill loses roughly 15–20% when properly compacted, and freshly dumped uncompacted fill settles for years. That is why the calculator's waste default runs higher than for gravel.
What is "clean fill"?
Dirt with no construction debris, organic matter or contamination — some areas certify it. Free or cheap dirt with an unknown history is where foundations meet their worst problems.
Assumptions, sources and limits
- Loose density ≈ 110 lb/ft³ (≈ 1.5 tons/yd³) — varies with moisture and composition.
- Compaction/settlement handled through the waste factor; deep engineered fills need geotechnical input.
- Prices come only from your own input.
Quantity planning. Fill quality, compaction spec and clean-fill rules follow your site and municipality.