How to use this tool
- Measure the paved area — length × width, splitting irregular driveways into rectangles.
- Set the compacted thickness: 2 in for a resurface over sound asphalt, 3 in for a new light-duty driveway, 4–6 in total (two lifts) for vehicle loading on new base.
- Order by the ton — plants sell hot mix by weight and batch to your arrival time, so confirm the delivery slot when you book.
How the result is calculated
Volume = length × width × depth (all in matching units), × count, × your waste factor; 1 yd³ = 27 ft³. Weight = volume × loose density — this tool uses ≈ 145 lb/ft³ for asphalt, which lands at roughly 1.96 tons per cubic yard. Loose density varies with moisture and grading — quarry tickets and delivery slips are the real weight.
Asphalt is quoted and laid compacted — the tonnage here is the compacted weight at ≈ 145 lb/ft³ (≈ 1.96 tons/yd³). A 2 in compacted residential driveway is the working minimum; 3 in of base + 2 in of top mix is the common two-lift build.
Choosing the right numbers
Compacted thickness by job — and what 100 ft² of it weighs:
| Job | Compacted thickness | Tons per 100 ft² |
|---|---|---|
| Resurfacing over sound asphalt | 1.5–2 in | ≈ 0.9–1.2 |
| Residential driveway (light duty) | 2–3 in | ≈ 1.2–1.8 |
| Driveway base lift (over aggregate) | 3 in | ≈ 1.8 |
| Driveway wearing lift | 2 in | ≈ 1.2 |
| Heavy vehicles / RV pad | 4–6 in total | ≈ 2.4–3.6 |
Hot mix cools as it hauls — it must be compacted before it drops below roughly 175 °F, so thickness per lift stays in the 2–3 in band: thicker single lifts can't be rolled in time, thinner ones chill too fast. Two lifts (base mix + wearing mix) beat one thick lift on any driveway over 3 in.
Common mistakes to avoid
- Ordering loose thickness as compacted. Asphalt compacts roughly 25% — a "3 in loose" mat finishes near 2¼ in. Order by compacted thickness and tonnage, not loose depth.
- One 4 in lift on a driveway. It cools before the roller can finish it; split into 3 in base + 2 in wearing (or similar).
- Paving over soft or muddy base. Asphalt follows the ground — failures show as dips within a year. Fix the aggregate base first.
- Forgetting the delivery minimum. Many plants have a 2–5 ton minimum or charge short-load fees — patches often cost less with bagged cold patch.
Worked examples
Example — 12 × 40 ft driveway, 3 in compacted, 5% waste
480 ft² × 0.25 ft = 120 ft³ × 1.05 = 126 ft³ ≈ 9.1 yd³ × 145 lb/ft³ ÷ 2000 ≈ 9.1 tons — one full truck load territory; confirm the plant's truck capacity.
Example — 20 × 20 ft RV pad, two lifts 3 + 2 in
Base lift: 400 × 0.25 × 1.05 ≈ 105 ft³ ≈ 7.6 tons; wearing lift: 400 × 0.167 × 1.05 ≈ 70 ft³ ≈ 5.1 tons — ≈ 12.7 tons total.
Frequently asked questions
How many tons of asphalt do I need for a driveway?
A 12×40 ft driveway at 3 in compacted needs about 9 tons. Rule of thumb: one ton covers roughly 55 ft² at 2 in or 36 ft² at 3 in.
How much does a ton of asphalt cover?
At 2 in compacted, one ton covers ≈ 55–60 ft²; at 3 in, ≈ 36–40 ft². Thickness is the biggest lever — not the price per ton.
How thick should an asphalt driveway be?
2–3 in compacted for cars on a good base; 4–6 in total in two lifts for trucks or RVs. The aggregate base under it matters as much as the asphalt itself.
Assumptions, sources and limits
- Compacted hot-mix density ≈ 145 lb/ft³ (≈ 1.96 tons/yd³) — mix designs vary a few percent.
- Thickness entered is compacted thickness, not loose.
- Prices come only from your own input.
Quantity planning. Mix type, lift sequence and base prep follow the job spec.