How to use this tool
- Measure the formed section — width and depth are the inside form dimensions, length the beam's run.
- Count the bar lines from the drawing: how bars run the beam's length, top and bottom combined.
- Stirrup spacing comes from the drawing too — 8 in is a common interior zone; end zones often tighten. Use the average for ordering, not the maximum.
- Read steel and concrete lines separately — they're different suppliers, ordered on different days.
How the result is calculated
Volume = width × depth × length (inches divided by 144 for ft² of section), × beam count, × a 5% placing allowance. Bar length = beam length × bar lines × count × 1.1 (lap and anchorage allowance). Stirrups = length ÷ spacing + 1 per beam, each consuming roughly its perimeter — 2 × (width + depth) in feet plus a hook allowance — at #4 weight (0.668 lb/ft). The steel sizing itself is engineering; this counts and weighs the layout you already have.
Choosing the right numbers
Common residential-grade beam sections, per 10 ft of length:
| Section | Concrete per 10 ft | Typical role |
|---|---|---|
| 12 × 16 in | ≈ 0.49 yd³ | Grade beams, light framing support |
| 12 × 20 in | ≈ 0.62 yd³ | Longer spans, heavier loads |
| 12 × 24 in | ≈ 0.74 yd³ | Deep grade beams, pedestal caps |
| 16 × 24 in | ≈ 0.99 yd³ | Heavy framing support |
What the drawing owns and this tool doesn't: bar sizes and count against bending, stirrup tightening at supports, development lengths, and the cover that keeps steel off the forms. A beam is the most stress-concentrated element in residential concrete — quantities from here, structure from an engineer.
Common mistakes to avoid
- Ordering steel by feel. Beams eat steel fast — a 12×16 × 20 ft beam with 4 #5 lines and 8 in stirrups carries ~350 lb of steel. Count it, don't eyeball it.
- Forgetting stirrup hooks. Each stirrup wraps the cage — the perimeter figure here includes a hook allowance, but drawings with long anchorage add more.
- One spacing everywhere. End zones tighten; ordering to the loose spacing understates the count.
- Beam concrete on the slab ticket. Beams pour separately from slabs most times — separate lines keep the two pour days honest.
- Cover ignored in layout. Steel needs 1.5 in from forms; a cage that fills the section won't fit — bar count vs section is a fit check, not just a weight.
Worked examples
Example — 20 ft grade beam, 12×16 in, 4 lines of #5, stirrups @ 8 in
Volume = (12×16/144) × 20 × 1.05 = 28 ft³ ≈ 1.04 yd³. Bars: 20 × 4 × 1.1 = 88 ft of #5 ≈ 92 lb. Stirrups: ceil(20 ÷ 0.667) + 1 = 31 → 31 × 5.47 ft ≈ 169 ft ≈ 113 lb. Total steel ≈ 205 lb.
Example — three 12×24 beams, 16 ft each, 6 lines #6, stirrups @ 6 in
Volume = (12×24/144) × 16 × 3 × 1.05 = 100.8 ft³ ≈ 3.73 yd³. Bars: 16 × 6 × 3 × 1.1 = 317 ft of #6 ≈ 476 lb; stirrups: 33 per beam × 3 = 99 → 99 × 6.8 ft ≈ 673 ft ≈ 450 lb. Steel ≈ 926 lb ≈ 0.46 tons.
Frequently asked questions
How much concrete does a beam take?
Width × depth in inches ÷ 144 × length in feet, ÷ 27 for yards. A 12×16 in beam is 0.049 yd³ per foot — a 20 ft beam is about 1 yd³ with waste.
How do I count stirrups?
Beam length ÷ spacing + 1, per beam — then let the drawing's end-zone tightening add a few. The calculator splits the count and weighs the stirrup steel at #4.
What size beam do I need?
That's an engineering answer: span, load, and support conditions decide it. Common residential grade beams run 12×16 to 12×24 in — but sizing is the engineer's, quantity is yours.
Assumptions, sources and limits
- Plain rectangular beams; T-beams, tapered and flanged sections need their own section math.
- 5% placing allowance on concrete; 10% lap/anchorage allowance on longitudinal bars; stirrup perimeter includes a hook allowance.
- Stirrup weight at #4 (0.668 lb/ft) — drawings specify actual stirrup bar size.
- Bar sizes, counts, spacing and cover come from your drawings; this tool counts and weighs them.
- Prices come only from your own input.
Quantity tool for an existing design. Beam sizing and reinforcement are engineered work.